Solving Space Vendor Problems for the Chanhassen Recreation Center with Modernfold Operable Walls

w l hall company   Solving Space Vendor Problems for the Chanhassen Recreation Center with Modernfold Operable Walls

The Chanhassen Recreation Center went through something that every construction customer dreads; having a supplier go out of business in the middle of their project. When they called the W. L. Hall Company, they thought their only option was an expensive and messy total track tear out and reinstallation.

w l hall company   Solving Space Vendor Problems for the Chanhassen Recreation Center with Modernfold Operable Walls 2

Expecting the worst, Chanhassen Recreation Center Manager Jodi Sarles reached out to W. L. Hall for assistance with her partially installed 3 wall project from her now defuncted vendor. Part of her concern was the significant disruption soffit demolition and reconstruction would cause to her fully open facility.

w l hall company   Solving Space Vendor Problems for the Chanhassen Recreation Center with Modernfold Operable Walls3

We assured Jodi that we could adapt our system to work with the other vendor's track and that we could provide new, state of the art Modernfold Premier operable and movable walls with a minimum of disruption to her facility's operations.

w l hall company   Solving Space Vendor Problems for the Chanhassen Recreation Center with Modernfold Operable Walls4

This isn't the first time the W. L. Hall Company was called in to fix the problems of another sub-contractor. If we can help you or one of your clients deal with project problems caused by another sub-contractor, please give us a call. We are here to help!

Click on the image below to discover our wide-ranging portfolio of collaborative projects.

w l hall portfolio
w l hall company   Solving Space Vendor Problems for the Chanhassen Recreation Center with Modernfold Operable Walls
By Ira Hackner 15 May, 2024
Minnesota State Office Building Exterior Glazing Project
By Ira Hackner 09 May, 2024
Spotlight on the North Loop Green Project: Transforming the Minneapolis Skyline
By Ira Hackner 02 May, 2024
Lakewood Cemetery (Minneapolis) New Eco-Friendly Visitor Center Glass & Glazing Project
By Ira Hackner 18 Apr, 2024
Skyfold Mirage for Magnifi Financial's Maple Grove New Branch Office
By Ira Hackner 10 Apr, 2024
Orthopaedic Hospital of Wisconsin (OHOW) Center at UW-Milwaukee Kalwall Translucent Panel System
By Ira Hackner 02 Apr, 2024
W. L. Hall Company | Window Renovation Project Spotlights
By Ira Hackner 21 Mar, 2024
Tartan High School (Oakdale, MN) | Effortless space reconfiguration for the school's four multipurpose rooms
W. L. Hall Company 2024 MOD Rate is at our all-time low of 0.60
By Ira Hackner 18 Mar, 2024
W. L. Hall Company 2024 MOD Rate is at our all-time low of 0.60
By Ira Hackner 12 Mar, 2024
Hazelden Betty Ford Foundation Facility (Center City, MN) New Wood Curtainwall System Project
By Ira Hackner 05 Mar, 2024
Women in Construction Week Spotlight - March 3 - 9, 2024 Heather Isaacson | Head of Engineering ๏ปฟ W. L. Hall Company
More Posts
Share by: